NOTICE: Issuance of Addendum No. 1 for the "Construction of the Main Irrigation Canal from the Maiden Tower Reservoir Project"
The Administration of Facilities Under Construction PLE under the Azerbaijan State Water Resources Agency hereby announces the issuance of Addendum No. 1 and the revised Bill of Quantities (BoQ) for the "Construction of the Main Irrigation Canal from the Maiden Tower Reservoir Project" (ICB Identification No.: AZE-1024 ICB/MC Open-01).
Key Revisions:
Revised Bid Submission Deadline: Extended from October 20, 2026, to November 10, 2026, at 12:00 (local time).
Revised Bid Opening Date: Rescheduled to November 11, 2026, at 15:00 (local time).
Bid Validity & Security Expiration: Bid validity is extended to March 10, 2027, and the Bid Security must remain valid until April 07, 2027.
Bill of Quantities (BoQ) Amendments: Quantity and unit adjustments have been made for pedestrian crossings and other relevant sections.
Addendum No. 1 and the revised BoQ have been officially transmitted to all registered bidders. All prospective bidders are strictly required to take these documents into full account when preparing their final proposals.